Perth, Dec 18, 2015 AEST (ABN Newswire) - MZI Resources Ltd (googlechartASX:MZI) is pleased to announce that it has completed commissioning and performance testing of the dedicated processing annexe constructed at the Picton Mineral Separation Plant (MSP), located near Bunbury in Western Australia. Consequently, operational responsibility for the MSP has been handed over to Doral Mineral Sands Pty Ltd (Doral), the MSP owner and with whom MZI has a long term processing agreement.

- Performance testing of Picton Mineral Separation Plant successfully completed

- Commissioning of main Keysbrook and Picton plant facilities now complete

- Commissioning of both facilities achieved in 7 weeks

- Loading of first shipment of zircon concentrate underway

Keysbrook Heavy Mineral Concentrate (HMC) was fed to the MSP from late November to mid-December, with each of the production circuits in the MSP successfully commissioned to design rates, or to agreed limits.

GR Engineering Services Ltd (GR Engineering), which constructed the annexe at the MSP, has now demobilised from site and is working towards delivery of final documentation to formally close out its contractual commitments with MZI.

It has taken only 7 weeks to successfully commission both the Wet Concentrator Plant (WCP) and MSP facilities after commissioning of the WCP began in late November.

Transmin Pty Ltd and MZI continue to work together to complete final commissioning of the Keysbrook Mine Feed Unit.

Loading of Keysbrook's first shipment of zircon concentrate is underway, with dispatch on track to occur in the next few days.

MZI Managing Director Trevor Matthews said "The hard working Keysbrook team continues to deliver exceptional results, with performance testing now largely completed at both sites. The support that has been provided by Doral and GR Engineering to achieve this excellent outcome is indicative of the strong relationship MZI has established with both parties. With the loading of our first shipment underway, we look forward to entering 2016 with Keysbrook fully operational."

Keysbrook is designed to produce approximately 96,000 dry tonnes of leucoxene products and zircon concentrate annually.


About MZI Resources Ltd

MZI Resources Ltd ASX MZI MZI Resources Ltd (ASX:MZI) is a mineral sands company focused on the high value minerals of zircon, rutile and leucoxene based in Perth, Western Australia. Its flagship operating asset is the Keysbrook Mineral Sands Project, located 70km south of Perth. At the Keysbrook mine, mineral sands are mined and processed to produce heavy mineral concentrate (HMC) which is processed into final products under a toll treating arrangement with Doral Mineral Sands Pty Ltd at the Picton Mineral Separation Plant (MSP) near Bunbury.

The Keysbrook mine hosts a world-class zircon / leucoxene ore body with total Ore Reserves equivalent to over 15 years of production at design output rates, and total Mineral Resources equivalent to over 30 years of production. Production commenced in late 2015, making the Keysbrook Project Australia’s first – and the world’s largest - primary producer of high value leucoxene.

https://www.facebook.com/pages/MZI-Resources/339204186112892 abnnewswire.com 


Contact

Trevor Matthews
Managing Director
T: +61-8-9328-9800



ABN Newswire
ABN Newswire This Page Viewed:  (Last 7 Days: 4) (Last 30 Days: 29) (Since Published: 3540)