Adelaide Energy Limited (ASX:ADE) Otway Petroleum Project Testing Program Update
Adelaide Energy Limited (ASX:ADE) Otway Petroleum Project Testing Program Update

Adelaide, June 23, 2010 AEST (ABN Newswire) - The Otway Petroleum Project is Adelaide Energy Ltd's (googlechartASX:ADE) 100% owned suite of integrated production, development and exploration oil and gas assets, which are located in the South Australian section of the onshore Otway Basin.

ADE has recently drilled and completed a number of wells as part of its Otway Petroleum Project. This report provides the final in a series of weekly reports on the ongoing testing and analysis program on those wells. Material developments will now be reported as they arise.

TESTING PROGRAM REPORT TO 0600 hrs 23 June 2010

Jacaranda Ridge-2

- The extended production test for Jacaranda Ridge-2 (JR-2) has commenced successfully

- Current flow rates to the Katnook Plant from both JR-2 and Limestone Ridge-1 are around 5,000,000 standard cubic feet of gas and 170 barrels of condensate per day

Patrick-1 and Hollick-1

- Pressure monitoring of these wells is continuing during the extended production test described above to demonstrate connectivity

Wynn-2

- No developments

Safety issues

- None

Environmental issues

- None

Contact

Carl Dorsch
Managing Director
Adelaide Energy Limited
Mob:+61-0400-508-088
Email: c.dorsch@adelaideenergy.com.au

Neil Young
Chief Commercial Officer
Adelaide Energy Limited
Mob: +61-0417-850-245
Email: neil.young@adelaideenergy.com.au



ABN Newswire
ABN Newswire This Page Viewed:  (Last 7 Days: 4) (Last 30 Days: 25) (Since Published: 3016)