Sydney, June 8, 2010 AEST (ABN Newswire) - Buccaneer Energy Limited (
ASX:BCC) (
PINK:BCGYF) is pleased to provide the following operational update.
VICK # 2
Sub-surface pumping equipment has been successfully installed. Surface pumping equipment will commence installation on Thursday 10 June after which pumping operations will commence.
VICK # 1
Completion rig has moved to the well site to commence installation of sub-surface pumping equipment which is expected to take approximately 5 days. On completion surface pumping equipment will be installed and pumping operations will commence.
The participants in the Lee County project are as follows:
Participant Working InterestBuccaneer Resources* 52.50%Sandstone Energy 38.75%Megashine International Ltd 8.75%
* A wholly owned subsidiary of Buccaneer Energy Limited