Adelaide, Jan 14, 2009 AEST (ABN Newswire) - Beach Petroleum Limited (ASX:BPT)(PINK:BEPTF) announce the drilling report for the week ending ending 14 January, 2009 are attached. Highlights of the week's activities include:

Beach Petroleum Operated Cooper / Eromanga Exploration

Gunyah-1, the third of four back-to-back wells currently being drilled by the Joint Venture in PEL 92 / PPL 220, is drilling ahead at a depth of 2005 metres in the Kalladeina Formation. Interests in the four well program are Beach Petroleum Ltd (75%) and Cooper Energy Ltd (25%).

Cooper/Eromanga Oil Exploration and Development - Santos Operated

In areas operated by Santos, two successful wells were drilled (Spencer West-3, Beach 20.21% and Tennaperra-2, Beach 30%).

Beach Operated Offshore Australia Program - SE Australia

Fermat-1 (Beach 50%) is being plugged and abandoned, having reached a total depth of 3585 metres and failing to find any significant hydrocarbons. Interests in Fermat-1 are Beach Petroleum Ltd, 50%, Essential Petroleum Resources Ltd, 25% and Mitsui E&P Australia Pty Ltd, 25%. Note that Essential is currently in default of the December 2008 and January 2009 cash call requirements for the Fermat-1 drilling operations.

Egypt - South East July Concession - Gulf of Suez

South July-1, targeting oil in the Rudeis and Nubia Formations, is drilling ahead in the South Gharib Formation at a depth of 2416m. Interests in South July-1 are Beach Petroleum (Egypt) Pty Limited, 20%, Santos Egypt Pty Ltd, 40% and Dana Petroleum (E&P) Limited, 40%.
------------------------------------Well                    Participants------------------------------------ South July-1            BPT     20.00% SE July Concession      STO*    40.00% Oil Exploration Well    DNX     40.00% Gulf of Suez,  Egypt                                    ---------------------------------------------------------------Weekly Progress & Summary                       Primary Targets---------------------------------------------------------------Report Time:    0600hrs (Egypt) 13/01/2009      Rudeis FormationDepth:          2416m                           Nubia SandstoneOperation:      Drilling ahead in the South Gharib FormationProgress:       1302m   ------------------------------------ Well                    Participants ------------------------------------  Fermat-1                BPT*    50.00%   VIC/P46                 EPR**   25.00%   Gas Exploration         MIT     25.00%   Otway Basin, Vic                         --------------------------------------------------------------- Weekly Progress & Summary                       Primary Targets ---------------------------------------------------------------Report Time:    0800 (AEST) 14/01/2009          Waarre FormationDepth:          3585m MDRT (TD)                 Flaxman FormationOperation:      Well is being plugged and abandoned.           Progress:       0m                                                                                      ------------------------------------Well                    Participants------------------------------------Gunyah-1                BPT*    75.00%PEL 92                  COE     25.00%Oil Exploration                       C/E Basin, SA                         ---------------------------------------------------------------Weekly Progress & Summary                       Primary Targets---------------------------------------------------------------Report Time:    0600 hrs (CST) 14/01/2009       Namur SandstoneDepth:          2005m                     Operation:      Drilling ahead in the Kalladeina FormationProgress:       2005m                     ------------------------------------Well                    Participants------------------------------------Spencer West-3          BPT     20.21%PPL 53                  STO*    66.60%Oil Appraisal           ORG     13.19%C/E Basin, SA                         ---------------------------------------------------------------Weekly Progress & Summary                       Primary Targets---------------------------------------------------------------Report Time:    0600 hrs (CST) 14/01/2009       McKinlay Member  Depth:          1726m (TD)                      Namur, Hutton (s)Operation:      Well is to be cased and suspended as a future McKinlay                Member and Namur Sandstone oil producer.Progress:       0m                                                                ------------------------------------Well                    Participants------------------------------------Tennaperra-2            BPT     30.00%PL 168                  STO*    70.00%Oil Appraisal                         C/E Basin, SA                         ---------------------------------------------------------------Weekly Progress & Summary                       Primary Targets---------------------------------------------------------------Report Time:    0600 hrs (CST) 14/01/2009       Hutton SandstoneDepth:          1724m (TD)                      Namur Sandstone (s)Operation:      Well has been cased and suspended as a future multi                zone oil producer.                        Progress:       230m                                ------------------------------------Well                    Participants  ------------------------------------Kanowana-7              BPT     20.21% PPL 28                  STO*    66.60% Gas Development         ORG     13.19% C/E Basin, SA                          ---------------------------------------------------------------Weekly Progress & Summary                       Primary Targets---------------------------------------------------------------Report Time:    0600 hrs (AEST) 14/01/2009      Tirrawarra SandstoneDepth:          3144m (TD)                      Patchawarra Fm (s)Operation:      Well has been cased and suspended as a future                     Patchawarra Formation and Tirrawarra Sandstone gas                and oil producer.                           Progress:       137m                      ------------------------------------  Well                    Participants          ------------------------------------                 Tirrawarra-77           BPT     20.21% PPL20                   STO*    66.60% Gas Development         ORG     13.19% C/E Basin, SA                          ---------------------------------------------------------------Weekly Progress & Summary                       Primary Targets---------------------------------------------------------------Report Time:    0600 hrs (CST) 14/01/2009       Patchawarra FmDepth:          2100m                           Tirrawarra SstOperation:      Drilling ahead in the Birkhead Formation.Progress:       2100m                                           --------------------------------COAL SEAM GAS PROJECTS          Location            Participants--------------------------------PL 198                  BPT     40%Coal Seam Develop't     AOE*    60%Surat  Basin, QLD                  --------------------------------------------------------------------Well         Depth       Operation: 0600hrs (EST) 14th January 2009--------------------------------------------------------------------Tipton- 146     341m    Drilling production zone.

* Operator
(s) Secondary Targets
COE Cooper Energy Resources
MIT Mitsui E&P Australia
AOE Arrow Energy NL
DNX Dana Petroleum (E&P) Limited
ORG Origin Energy Resources LTD
BPT Beach Petroleum Ltd
EPR Essential Petroleum Resources Ltd
STO Santos Limited

Contact

Reg Nelson
Beach Petroleum
08 8338 2833

Mark Lindh
Adelaide Equity
0414 551 361

Ian Howarth
Farrington National
03 9223 2455



ABN Newswire
ABN Newswire This Page Viewed:  (Last 7 Days: 6) (Last 30 Days: 11) (Since Published: 1646)