Carnarvon Energy Ltd Stock Market Press Releases and Company Profile
Phoenix South-3 Drilling Update
Phoenix South-3 Drilling Update

Perth, July 24, 2018 AEST (ABN Newswire) - Carnarvon Petroleum Limited ("Carnarvon") (googlechartASX:CVN) (googlechartCVONF:OTCMKTS) is pleased to provide the following update on the drilling of the Phoenix South-3 ("PS-3").

Progress

The 9-5/8" casing has been set and cemented in place down to around 5,165 metres Measured Depth ("MD") and the well has drilled down to around 5,208 metres MD.

The results to date have been consistent with those encountered in Phoenix South-2.

Current Operations

The rig is currently preparing to set a 7-5/8" liner.

Forward Plan

After setting the liner the well will drill ahead in 6-1/8" hole to a planned depth of approximately 5,500 metres MD.

Controlled Drilling through Reservoir section

The previously drilled Phoenix South-2 ("PS-2") well was unable to fully evaluate the Caley Member due to high pressures encountered in that well. The PS3 well plan and its associated procedures employ controlled drilling operations prior to and during the drilling of the reservoir section. As a consequence, drilling progress will be slower than that previously experienced in the other wells in the Phoenix project.

Well Objective

The primary objective for the Phoenix South-3 well is to evaluate the gas and condensate potential of the Caley Member within a large, faulted anti-clinal closure that was partially penetrated with the Phoenix South-2 well.

Phoenix South-2 encountered gas and condensate in the Caley Member but was unable to drill through and evaluate the formation. The Phoenix South-3 well has been optimally designed to penetrate and evaluate the hydrocarbon bearing formations of the Caley Member.

Phoenix South-3 is located around 560 metres North-North East of the Phoenix South-2 well. The well will target a closure that is estimated by Carnarvon to contain a gross mean recoverable prospective resource of 489 Bscf of gas and 57 million barrels of associated condensate (being 143 million barrels of oil equivalent ("boe"), gross, Pmean) - Refer to ASX Announcement on 28 March 2017.

Prospective Resources are the estimated quantities of petroleum that may potentially be recovered by the application of a future development project and may relate to undiscovered accumulations. These prospective resource estimates have an associated risk of discovery and risk of development. Further exploration and appraisal (including this well) is required to determine the existence of a significant quantity of potentially moveable hydrocarbons.
 Project equity Owners: Carnarvon Petroleum          20% Quadrant Energy (Operator)   80% 

To view figures, please visit:
http://abnnewswire.net/lnk/010H5AG3


About Carnarvon Energy Ltd

Carnarvon Energy Limited is an oil and gas exploration company, listed on the Australian stock exchange (ASX:CVN), Frankfurt (FRA:CJB) and US OTC (OTCMKTS:CVONF). Carnarvon has an extensive acreage position in the North West Shelf of Western Australia that is designed to offer investors high alpha leverage to the energy sector. The company's near term focus is on maturing oil, gas and condensate discovered in its Phoenix project, with partner Quadrant Energy, and on bringing into production oil from the Buffalo field.

https://www.linkedin.com/company/carnarvon-petroleum-ltd/ abnnewswire.com 


Contact

Investor inquiries:
Thomson Naude
Company Secretary
Phone: +61-8-9321-2665
Email: investor.relations@cvn.com.au

Media inquiries:
Luke Derbyshire
Managing Director, Spoke Corporate
Phone: +61-488-664-246
Email: luke@spokecorporate.com



ABN Newswire
ABN Newswire This Page Viewed:  (Last 7 Days: 9) (Last 30 Days: 25) (Since Published: 4670)