Kidston Solar Phase One 50MW Update
Kidston Solar Phase One 50MW Update

Sydney, May 15, 2017 AEST (ABN Newswire) - Genex Power Limited (googlechartASX:GNX) (Genex or Company) is pleased to provide shareholders with this latest update regarding the construction program for the Company's Phase One 50MW Kidston Solar Project (KSP1 or Project).

Genex advises that the construction of KSP1 continues to remain on time and on budget for first generation in Q4 2017 and Practical Completion in Q1 2018. Key activities since the last update (refer ASX announcement 20 April 2017) include:

- First delivery of First Solar Thin-Film solar modules complete;
- First delivery of NEXTracker components underway;
- Piling rigs mobilized to site ahead of pile delivery;
- Ergon switchyard equipment 75% installed and equipment earthing underway;
- Solar farm substation earth-grid installed;
- Laydown area for materials storage and component assembly 100% complete; and
- Site clearing approximately 90% complete.

Commenting on the recent progress of KSP1, Managing Director of Genex Power Michael Addison said, "Genex's focus on project delivery continues with the project continuing to perform to budget. Kidston is now a hive of activity with 65 people employed on site. The outlook for wholesale electricity and Large-scale Generation Certificates (LGCs) remains robust which underpins the potential to deliver strong cash flows to Genex".

The Federal Government, through the Australian Renewable Energy Agency has provided $8.9 million funding to support the construction of the $126 million Project at Genex's Kidston Solar Farm.

To view figures, please visit:
http://abnnewswire.net/lnk/8XPF6PS4


About Genex Power Ltd

Genex Power Ltd ASX:GNXGenex Power Limited (ASX:GNX) is focused on developing a portfolio of renewable energy generation and storage projects across Australia. The Company's flagship Kidston Clean Energy Hub, located in north Queensland, will integrate large-scale solar generation with pumped storage hydro. The Kidston Clean Energy Hub is comprised of the operating 50MW stage 1 Solar Project (KS1) and the 250MW Kidston Pumped Storage Hydro Project (K2-Hydro) with potential for further multi-stage wind and solar projects. The 50MW Jemalong Solar Project (JSP) is located in NSW and provides geographical diversification to the Genex Power Limited portfolio. JSP was energised in early December 2020 and commissioning is now underway. Genex is further developing its energy storage portfolio via the early stage development of a 50MW/75MWh standalone battery energy storage system at Bouldercombe in Queensland. With over 400MW of renewable energy and storage projects in development, Genex is well placed as Australia's leading renewable energy and storage company.

https://twitter.com/Genex_Power https://www.facebook.com/genexpowerlimited/ https://www.youtube.com/channel/UC0p4njH5MsRCfphzaZ2XLCA https://www.linkedin.com/company-beta/10858225?pathWildcard=10858225 abnnewswire.com 


Contact

Simon Kidston
Executive Director
Tel: +61 2 9048 8850
Email: sk@genexpower.com.au



ABN Newswire
ABN Newswire This Page Viewed:  (Last 7 Days: 2) (Last 30 Days: 21) (Since Published: 5473)